What the Committee of Adjustment approves, and how long it takes

Toronto’s Committee of Adjustment decides whether a project that does not quite fit the zoning by-law may go ahead anyway. It approves 90.8% of the applications it decides. It takes a median of 120 days to do it — and that clock runs before a building permit can be applied for, not alongside it.

For the whole timeline on your project, committee then permit, use the permit timeline for your type of work and ward.

Applications on record
41,1582016 to today
Approved
90.8%31,860 of 35,087 decided
Refused
9.2%3,227 applications
Median time to a decision
120 days33,791 closed applications

What this does to the permit timeline

The headline number on this site is that half of Toronto building permits are issued within 27 days of the application. That is the whole answer only for a project that needs no variance. Where one is needed, the committee has to decide first: a median of 120 days, then the permit’s 27. Back to back, about 147 days, not 27.

The two medians come from different sets of applications and cannot be added to produce a single project’s wait. They are a realistic order of magnitude for a project that needs both steps, and a correction to the impression the permit figure alone gives. See permit wait times for the second half of that.

Applications by year filed

  • 2017 4,826 applications
  • 2018 4,056 applications
  • 2019 3,785 applications
  • 2020 3,287 applications
  • 2021 4,091 applications
  • 2022 3,564 applications
  • 2023 3,024 applications
  • 2024 3,122 applications
  • 2025 2,833 applications
  • 2026 2,047 applications

2026 is a part year and will keep filling until it closes.

Approval rate by type of work

Type of work Approved Applications decided
Splitting one lot into two 78.0% 1,980
Moving land from one lot to its neighbour 83.5% 291
New home 87.1% 12,063
Legalising something already built 89.1% 110
New commercial or industrial building 89.6% 278
Other 92.4% 6,039
Addition to a home 95.0% 12,966
Addition to a commercial or industrial building 96.0% 940
Re-establishing a right of way 96.4% 28
Correcting the title to a property 97.9% 47
Creating a right of way over the land 97.9% 286
A lease longer than 21 years 100.0% 44

Splitting one lot into two is the hardest ask at 78.0% approved across 1,980 decisions; a lease longer than 21 years clears 100.0%. Types with fewer than 20 decisions are not shown. These are the City's own application categories, named here in plain English: it files them as “Sever Lot”, “Leases over 21 Years” and so on.

By ward

Ward Median days Approved Applications
Toronto Centre 154 94.6% 651
Spadina-Fort York 149 94.2% 920
Beaches-East York 147 90.7% 2,590
University-Rosedale 147 90.3% 2,450
Toronto-Danforth 145 91.8% 3,006
Toronto-St. Paul's 143 91.9% 2,507
Davenport 135 92.5% 2,204
Parkdale-High Park 133 93.8% 2,207
Scarborough Southwest 120 88.9% 2,604
Scarborough-Agincourt 113 86.5% 406
Scarborough North 113 88.6% 320
Scarborough-Rouge Park 107 89.7% 751
Etobicoke-Lakeshore 105 88.6% 3,888
Scarborough Centre 104 94.6% 711
Scarborough-Guildwood 104 91.3% 405
Willowdale 101 83.8% 2,209
Don Valley West 98 89.5% 2,609
Don Valley North 98 93.3% 585
Don Valley East 97 93.6% 681
Etobicoke North 97 94.9% 595
Eglinton-Lawrence 95 90.0% 3,059
York South-Weston 94 92.3% 1,622
York Centre 93 90.2% 1,121
Humber River-Black Creek 93 94.2% 382
Etobicoke Centre 86 95.1% 1,609

Toronto Centre takes longest at 154 days; Etobicoke Centre is quickest at 86. On approval, Willowdale is the strictest at 83.8% and Etobicoke Centre the most permissive at 95.1%.

Neighbourhoods with the most applications

Neighbourhood Applications Approved Median days
Stonegate-Queensway 946 93.9% 91
Bedford Park-Nortown 916 88.9% 96
Birchcliffe-Cliffside 903 92.4% 106
The Beaches 751 90.9% 153
South Riverdale 740 92.1% 146
Annex 727 91.0% 146
Lawrence Park South 689 89.1% 97
Leaside-Bennington 685 89.8% 95
Danforth East York 661 88.5% 146
Lansing-Westgate 656 80.7% 104
Alderwood 621 87.6% 156
Long Branch 613 69.2% 196
Clairlea-Birchmount 611 83.4% 157
High Park-Swansea 611 93.7% 133
Rosedale-Moore Park 602 91.5% 142
Islington 597 93.2% 91
Trinity-Bellwoods 572 91.2% 146
Lawrence Park North 558 87.8% 94
Banbury-Don Mills 558 92.8% 94
East Willowdale 530 86.8% 104
Oakwood Village 522 93.0% 131
Mount Pleasant East 516 90.4% 108
Mimico-Queensway 468 92.7% 98
Humewood-Cedarvale 468 92.3% 142
Forest Hill South 459 91.5% 152

The 25 neighbourhoods with the most applications on record, of Toronto’s 158.

How this is measured

Counted from the City’s Committee of Adjustment application datasets: active applications, those closed since 2017, and a 2016 back-file. 41,158 applications carry a street name and are counted here. They are placed on a ward, neighbourhood and street by the same address match the permit pages use, which resolves 97% of them.

The approval rate counts only applications the committee actually decided — approved or refused. Withdrawn and deferred applications are left out of the rate rather than counted as refusals, which would overstate how often the committee says no. The City writes the decision as free text, so “approved”, “granted”, “approved on condition” and “conditional approval” are read as the same outcome.

Only the closed-since-2017 file records a final decision date, so every median on this page is measured over those applications and no earlier ones. The median is calendar days from the date the application was received to the date the file was closed, which includes the wait for a hearing date. A page shows a rate or a median only where at least 20 applications support it. Latest permit on file: Nov 8, 2026. Source and caveats: method.

Whether a given project needs a variance at all is a zoning question this data cannot answer. The City explains the committee’s role and how to apply at toronto.ca.