How long a Toronto building permit takes

Half of all Toronto building permits are issued within 27 days of the application. That is the median across 937,334 permits the City has actually issued. The wait is not the same for everyone: new building runs to 86 days, and where you build moves it by weeks.

Planning a project? The permit timeline gives the figure for your type of work in your ward, from permits issued in the last three years.

Median wait, all permits
27 days937,334 issued permits
Median wait, 2026
28 days11 days off the 2023 peak
Peak wait
39 days2023
Slowest type of work
86 daysNew Building

Median days from application to issue, by year issued

  • 2005 29 days · 27,259 permits
  • 2006 15 days · 22,549 permits
  • 2007 22 days · 25,105 permits
  • 2008 22 days · 32,203 permits
  • 2009 20 days · 25,850 permits
  • 2010 23 days · 33,936 permits
  • 2011 21 days · 32,169 permits
  • 2012 28 days · 35,175 permits
  • 2013 27 days · 41,950 permits
  • 2014 20 days · 41,466 permits
  • 2015 23 days · 43,186 permits
  • 2016 26 days · 45,467 permits
  • 2017 28 days · 46,091 permits
  • 2018 28 days · 44,000 permits
  • 2019 29 days · 40,522 permits
  • 2020 34 days · 32,751 permits
  • 2021 33 days · 35,173 permits
  • 2022 38 days · 34,760 permits
  • 2023 39 days · 32,991 permits
  • 2024 30 days · 31,813 permits
  • 2025 29 days · 32,987 permits
  • 2026 28 days · 27,110 permits

Waits climbed from 29 days in 2019 to 39 in 2023, then fell back to 28 in 2026. 2026 is a part year: permits applied for recently and not yet issued cannot be counted, which pulls a current year's median down until it settles.

By type of work

The 25 types with the most issued permits. New Building is the slowest at 86 days; porch clears in 5.

By ward

Ward Median days Permits measured
Scarborough-Rouge Park 52 23,139
Scarborough North 51 19,869
Humber River-Black Creek 51 17,303
Scarborough Southwest 48 33,984
Scarborough-Agincourt 38 14,337
Scarborough Centre 35 21,820
Etobicoke North 35 18,678
Etobicoke-Lakeshore 34 54,031
York Centre 33 27,197
Scarborough-Guildwood 33 12,606
Willowdale 29 38,749
York South-Weston 29 28,360
Don Valley East 29 20,574
Don Valley North 28 17,712
Spadina-Fort York 24 63,002
Eglinton-Lawrence 23 58,108
Toronto Centre 23 41,703
Etobicoke Centre 23 31,932
Don Valley West 22 47,942
Toronto-St. Paul's 21 44,072
University-Rosedale 20 69,260
Beaches-East York 18 45,737
Davenport 17 39,916
Toronto-Danforth 16 51,130
Parkdale-High Park 15 40,427

Scarborough-Rouge Park is the slowest ward at 52 days; Parkdale-High Park the fastest at 15. A ward's mix of work explains much of that: wards with more new builds wait longer.

How this is measured

Each permit is counted once, from the date it was first applied for to the date it was first issued. A revised permit carries a new application date on every revision row; measuring from the latest revision would report the revision's turnaround, not the applicant's, and would make the median look roughly a third shorter than it is.

Only issued permits can be measured, so anything still in the queue is absent, and a long-running application is counted on the day it finally clears. 937,334 of the City's 997,873 permits carry both dates. Waits of more than 2,000 days, and the 0.01% of records issued before they were applied for, are dropped as data errors. A page shows a median only where at least 20 of its permits were issued.

These are calendar days, not business days, and they measure the City's record, not the applicant's experience: time spent preparing drawings or answering a request for more information sits inside the same window. Latest permit on file: Nov 8, 2026. Source and caveats: method.

Source
City of Toronto Open Data