How long a Toronto building permit takes

Half of all Toronto building permits are issued within 27 days of the application. That is the median across 933,432 permits the City has actually issued. The wait is not the same for everyone: new building runs to 86 days, and where you build moves it by weeks.

Median wait, all permits
27 days933,432 issued permits
Median wait, 2026
29 days10 days off the 2023 peak
Peak wait
39 days2023
Slowest type of work
86 daysNew Building

Median days from application to issue, by year issued

  • 2005 29 days · 27,259 permits
  • 2006 15 days · 22,549 permits
  • 2007 22 days · 25,105 permits
  • 2008 22 days · 32,203 permits
  • 2009 20 days · 25,850 permits
  • 2010 23 days · 33,936 permits
  • 2011 21 days · 32,169 permits
  • 2012 28 days · 35,174 permits
  • 2013 27 days · 41,950 permits
  • 2014 20 days · 41,466 permits
  • 2015 23 days · 43,186 permits
  • 2016 26 days · 45,468 permits
  • 2017 28 days · 46,091 permits
  • 2018 28 days · 44,000 permits
  • 2019 29 days · 40,522 permits
  • 2020 34 days · 32,751 permits
  • 2021 33 days · 35,173 permits
  • 2022 38 days · 34,761 permits
  • 2023 39 days · 32,991 permits
  • 2024 30 days · 31,813 permits
  • 2025 29 days · 32,988 permits
  • 2026 29 days · 23,206 permits

Waits climbed from 29 days in 2019 to 39 in 2023, then fell back to 29 in 2026. 2026 is a part year: permits applied for recently and not yet issued cannot be counted, which pulls a current year's median down until it settles.

By type of work

The 25 types with the most issued permits. New Building is the slowest at 86 days; porch clears in 5.

By ward

Ward Median days Permits measured
Scarborough-Rouge Park 52 23,074
Scarborough North 51 19,829
Humber River-Black Creek 51 17,223
Scarborough Southwest 48 33,831
Scarborough-Agincourt 38 14,264
Scarborough Centre 35 21,707
Etobicoke North 35 18,581
Etobicoke-Lakeshore 34 53,784
York Centre 33 27,090
Scarborough-Guildwood 33 12,522
Willowdale 29 38,555
York South-Weston 29 28,289
Don Valley East 29 20,497
Don Valley North 28 17,622
Spadina-Fort York 24 62,748
Eglinton-Lawrence 23 57,918
Don Valley West 23 47,780
Etobicoke Centre 23 31,838
Toronto Centre 22 41,538
Toronto-St. Paul's 21 43,859
University-Rosedale 20 68,964
Beaches-East York 18 45,529
Davenport 17 39,709
Toronto-Danforth 16 50,862
Parkdale-High Park 15 40,245

Scarborough-Rouge Park is the slowest ward at 52 days; Parkdale-High Park the fastest at 15. A ward's mix of work explains much of that: wards with more new builds wait longer.

How this is measured

Each permit is counted once, from the date it was first applied for to the date it was first issued. A revised permit carries a new application date on every revision row; measuring from the latest revision would report the revision's turnaround, not the applicant's, and would make the median look roughly a third shorter than it is.

Only issued permits can be measured, so anything still in the queue is absent, and a long-running application is counted on the day it finally clears. 933,432 of the City's 993,479 permits carry both dates. Waits of more than 2,000 days, and the 0.01% of records issued before they were applied for, are dropped as data errors. A page shows a median only where at least 20 of its permits were issued.

These are calendar days, not business days, and they measure the City's record, not the applicant's experience: time spent preparing drawings or answering a request for more information sits inside the same window. Latest permit on file: Sep 23, 2026. Source and caveats: method.