thepermitmap

Tool · permits issued 2024–2026

How long will my permit take?

Half of the 91,910 Toronto permits issued since 2024 came within 29 days of the application, 3 in 4 within 66. Pick your work and ward to see yours.

Does it need a minor variance?
Half are issued within
29 days91,910 permits
3 in 4 are issued within
66 daysa quarter take longer
The fastest quarter
8 daysor less

All permits issued in Toronto since 2024, measured from first application to first issue.

If the project needs a minor variance

A project that breaks a zoning rule, such as building closer to the lot line than the by-law allows, needs a minor variance from the Committee of Adjustment first. The permit can only be applied for once the committee has decided. That step took a median of 120 days, so it usually takes longer than the permit itself. Details on toronto.ca; approval rates and decision times by ward are on the variances page.

Typical wait by type of work, issued since 2024

Type of work Half within 3 in 4 within Permits
Plumbing Building Permit Related(PS) 32 days 70 days 19,394
Mechanical Building Permit Related(MS) 36 days 74 days 16,705
Interior Alterations 24 days 45 days 11,750
Drain and Site Service Building Permit Related (DR) 35 days 98 days 7,654
Multiple Projects 31 days 70 days 5,578
Back Water Valve (Sewer only) 1 days 3 days 4,746
New Building 103 days 416 days 3,147
Demolition 69 days 148 days 2,693
Sign Building Permit Related 8 days 16 days 2,263
New Laneway / Rear Yard Suite 81 days 142 days 1,338
Building Additions/Alterations Other(BA) 40 days 73 days 1,231
Addition(s) 53 days 127 days 1,154
Party Wall Admin Permits 10 days 26 days 1,100
Small Residential Projects Other(SR) 14 days 39 days 1,091
Second Suite (New) 8 days 16 days 952
Plumbing Other(PS) 27 days 43 days 948
Deck 7 days 15 days 678
Electromagnetic Locks 6 days 20 days 676
Garage 7 days 13 days 664
Fire Alarm 27 days 34 days 592

The 20 types of work with the most permits issued since 2024. All-time medians, and the year-by-year trend, are on the wait times report.

How this is measured

Days run from the date a permit was first applied for to the date it was first issued, so a revision does not reset the clock. Only permits issued in 2024 or later count: waits moved by months between 2019 and 2023, and an all-time figure would describe a city that no longer exists. A type of work in one ward is shown only when at least 20 permits back it; below that the tool shows the type of work across the whole city and says so. The variance figure is the committee's median from application to decision, for that ward where it has enough decisions. Adding the two medians gives a typical end-to-end time, not a promise. Source and method: method.

Source
City of Toronto Open Data
Dataset
Building permits, active + cleared
Records
91,910
Refresh
Daily from the City
Sheet
TLS-01