Type of work · 16 of 103 by permit count
Other(BA) permits in Toronto
The City of Toronto has 9,726 other(ba) permits on record for Toronto, going back to 1985. Those permits created 493 homes and removed 7, a net change of +486. Declared construction value totals $3.9B. Half of the 8,712 permits issued here came through within 35 days of the application. The most recent permit was issued Oct 30, 2026 at 2 Minto St.
- Permits on record
- 9,7261985–2026
- Declared construction value
- $3.9Bas filed, not adjusted
- Homes created
- 493dwelling units
- Homes removed
- 7net +486
- Typical wait
- 35 days8 days slower than the city
Permits issued per year
Zoning
- Most common zone
- CR47.3% of permits · by-law 40.10
- In detached-house zones
- 2.4%35.6% below the city’s 38.0%
- Permits with a zone
- 6,279of 9,726 on record
The zoning categories the permits in Other(BA) fall in, under Zoning By-law 569-2013. These are the City's own category names. This counts permits, not land: it says where the building work happened under which rules, not how the area is carved up. What each zone allows, and what gets built in it.
Most common work
Structures worked on
Postal areas
Most recent permits
| Issued | Address | Work | What was filed | Value | Status |
|---|---|---|---|---|---|
| Oct 30, 2026 | 2 Minto St | Other(BA) | Frontyard Landscaping renovation involving the construction of planters and a new rear retaining wall above 1m height | $50K | Open |
| Oct 30, 2026 | 100 Regent Rd | Other(BA) | Exterior site improvements including front canopy for existing place of worship | $90K | Open |
| Oct 29, 2026 | 3224 Yonge St | Other(BA) | Proposal to remove two existing rooftop units and install new carrier replacements on custom curb adapters, with structural opening reinforcement, gas and electrical reconnection, new thermostats and controls, and balancing and commissioning. | $260K | Open |
| Oct 29, 2026 | 2885 Kennedy Rd | Other(BA) | Construction of a 20¿ (Length) x 11¿ (Width) x 10¿ (Height) single-storey, detached, pre-engineered steel-frame storage intended for private storage use. The structure will be situated on a reinforced concrete slab-on-grade foundation as per the attached engineered structural drawings | $45K | Open |
| Oct 29, 2026 | 4651 Sheppard Ave E | Other(BA) | Proposed construction of a noise barrier wall to protect the adjacent building from the noise and vibration generated by the construction activities. | $2.0M | Open |
| Oct 29, 2026 | 1200 Ellesmere Rd | Other(BA) | CONCRETE PAD FOOTING FOR SILO AND SILO | $5K | Open |
| Oct 28, 2026 | 1848 Avenue Rd | Other(BA) | Exterior restoration of suspended walkway, including concrete repairs and guardrail replacement. | $96K | Open |
| Oct 28, 2026 | 223 Carlton St | Other(BA) | Minor renovations involving, Installing a 12-foot-wide patio door/screen assembly in an enlarged opening on the second floor; Removing a small section of the partition wall on the ground floor; andRelocating a fire exit door within the existing wall. - Unit A | $15K | Open |
| Oct 28, 2026 | 65 Wynford Heights Cres | Other(BA) | Targeted exterior wall repairs and replacing exterior joint sealants at 65 Wynford Heights Crescent. Major work items include: Localized concrete repairs, targeted through-wall flashing installation, targeted masonry repairs and mortar repainting, sheet metal flashing installation at parapet walls a | $205K | Open |
| Oct 28, 2026 | 400 Greenwood Ave | Other(BA) | Proposal for interior alterations (replacement of pump pit access hatch, localized concrete repairs, alterations and installation of pit ladders and pump control rework). | $200K | Open |
| Oct 28, 2026 | 580 Commissioners St | Other(BA) | Proposal for removal of one(1) existing 45,600L diesel fuel aboveground storage tank, one(1) existing 15,000L gasoline fuel aboveground storage tank, and associated appurtenances. | $1.5M | Open |
| Oct 28, 2026 | 480 Front St W | Other(BA) | Structural slab infill at openings on L4&6. | $300K | Open |
| Oct 28, 2026 | 100 Queen St W | Other(BA) | REV: Proposed revision includes - Light structural repairs, concrete surface repairs, drainage replacement Structural rehab work for the Hagerman east and west stairs at City Hall (Nathan Philips Square) | — | Open |
| Oct 27, 2026 | 117 Pembroke St | Other(BA) | Proposal to construct pedestrian ramp. | $10K | Open |
| Oct 27, 2026 | 6351 Steeles Ave E | Other(BA) | Proposed review & design of buiding elements (egress, structural foundations/supports electrical & fire protection) for the new MHE/platform work | $573K | Open |
| Oct 27, 2026 | 2 Jane St | Other(BA) | Proposal for repair to concrete structure within the Toronto Hydro Vault as per the work order and in accordance with Toronto Hydro requirements. | $380K | Open |
| Oct 27, 2026 | 400 Carlingview Dr | Other(BA) | Proposal to install stand-alone steel storage pallet racks inside the warehouse. | $75K | Open |
| Oct 27, 2026 | 135 Ossington Ave | Other(BA) | Proposal for an administrative party wall permit for the work done on the shared party wall between 135 & 137 Ossington, for permit # 26 249378 BLD 00 BA | — | Open |
| Oct 27, 2026 | 200 King St E | Other(BA) | Demolition and reconstruction of staircase, podium slab, and wall with waterproofing repairs | $50K | Open |
| Oct 26, 2026 | 2700 Bathurst St | Other(BA) | Proposal to remove and replace building front door canopy. | $50K | Open |
| Oct 26, 2026 | 853 College St | Other(BA) | Revision 1: Proposed refacing of existing front facade | — | Open |
| Oct 26, 2026 | 160 Transit Rd | Other(BA) | Proposal for multiple projects (replace access hatches at pump pit, localized concrete repairs, install pit ladder and pump control rework). | $200K | Open |
| Oct 26, 2026 | 955 Queen St E | Other(BA) | Proposed window reqplacement within existing rough openings, new window frames will have slimmer profiles to increas the galzing area. | $20K | Open |
| Oct 26, 2026 | 1955 Steeles Ave E | Other(BA) | Extraction of the existing tension deficient post-tensioned cables within the tower¿s main (2nd), 4th, and roof level slabs; targeted replacement of tension deficient post-tensioned cables at the tower¿s main (2nd), 4th, and roof level slabs including replacing the post-tensioned anchors (includes r | $370K | Open |
| Oct 23, 2026 | 861 Dundas St W | Other(BA) | Revision TO AS BUILT SECOND & THIRD FLOOR WINDOWS AT SOUTH WALL AS PREVIOUSLY APPROVED, MAINTAIN AS BUILT GUARD RAIL AT NORTH & SOUTH ROOF DECK AND ADDED NEW WINDOW AT SECOND FLOOR WEST WALLMAINTAIN EXISTING BUILDING AS BUILT BY CONVERTING PARKING SPACE TO NON-RESIDENTIAL FLOOR AREA (AS APPROVED UND | — | Open |
| Oct 23, 2026 | 1292 Gerrard St E | Other(BA) | Proposal for rear deck | $5K | Open |
| Oct 23, 2026 | 380 The East Mall | Other(BA) | Proposal to install 4 EV Charging Stations, DC Battery Enclosure and 13m Lightpole in the parking log and landscape area.See also 24 193340 ZAP. | $200K | Open |
| Oct 21, 2026 | 123 Eglinton Ave E | Other(BA) | Wholesale replacement of exterior sealants. Wholesale replacement off vent grills. Localized masonry repairs including brick replacement and mortar joint repointing. Localized concrete balcony slab surface and slab edge repairs. Localized surface repairs at deteriorated EIFS cladding. | $1K | Open |
| Oct 21, 2026 | 4701-4719 BATHURST ST | Other(BA) | Proposed new outdoor gazebo with covered roof and open four sides. | $5K | Open |
| Oct 21, 2026 | 115 Winona Dr | Other(BA) | New water service & water leakage mitigation at existing Winona Drive Senior Public School. | $400K | Open |
| Oct 21, 2026 | 7 Glamorgan Ave | Other(BA) | DCW and DHWR Plumbing Header/Branches and Sanitary Drainage Headers/Stacks Offsets Replacement. In addition to Ground Floor and Top Floor Ceiling Replacement in the Hallways | $750K | Open |
| Oct 21, 2026 | 3464 Danforth Ave | Other(BA) | Proposal for a basement walk out and canopy at the rear | $10K | Open |
| Oct 21, 2026 | 1749 Albion Rd | Other(BA) | Tim Horton (100629) interior and exterior alterations. The exterior work will consist of mesh lighbox, repainting stucco finish and siding, new hockey stick door handles, new vinyl graphic above drive thru window, new exterior stamp sign c/w light, new c-channel, addition of wall sconces, replacing | $330K | Open |
| Oct 21, 2026 | 25 Bay Mills Blvd | Other(BA) | Replace existing garbage enclosure at rear of apartment building. | $50K | Open |
| Oct 20, 2026 | 643 Dupont St | Other(BA) | Localized removal and reconstruction of a portion of the existing exterior brick masonry wall at the side of the existing building, including associated masonry repairs and reinstatement.No change to the existing building use, footprint, or building area. | $39K | Closed |
| Oct 20, 2026 | 979 Albion Rd | Other(BA) | Proposed balcony construction | $25K | Open |
| Oct 20, 2026 | 1 Hickory Tree Rd | Other(BA) | Proposal for removal of existing retaining wall stones and installation of new retaining wall stones. | $59K | Open |
| Oct 19, 2026 | 10 Bay St | Other(BA) | Proposal for interior alterations (replacement of pump pit access hatch, localized concrete repairs and pump control rework). | $200K | Open |
| Oct 19, 2026 | 5050 Sheppard Ave E | Other(BA) | Proposal to add electronic level monitoring to one (1) existing 2,900 L volume Transformer Room Spill Tank (Tank MA1). Decommission and remove one (1) existing 2,325 L volume Flammable Storage Room Spill Tank (Tank ID MA2), piping, and associated appurtenances. Existing Veeder-Root TLS-450 console t | $550K | Open |
| Oct 19, 2026 | 610 University Ave | Other(BA) | Structural Repairs and Minor Mechanical Work at Rooftop Cooling Tower | $450K | Open |
The 40 most recent of 9,726 permits on record. Figures come from the City’s active and cleared permit datasets, refreshed daily — what that covers, and what it misses.