The City of Toronto has 216 building permits on record for Queen'S Park, going back to 1995. Declared construction value totals $215.0M. The most recent permit was applied for Sep 3, 2026 at 111 Queen's Park.
- Permits on record
- 2161995–2026
- Declared construction value
- $215.0Mas filed, not adjusted
- Homes created
- 0dwelling units
- Homes removed
- 0net +0
Permits issued per year
20002026 (part year)
Most common work
Structures worked on
Where this street runs
University 168 permits
Bay-Cloverhill 46 permits
Most recent permits
| Issued | Work | What was filed | Value | Status |
|---|---|---|---|---|
| Sep 3, 2026 | Fire Alarm | Proposal for fire alarm system panel repair. Edwards EST3 to EST4 | $25K | Open |
| Aug 28, 2026 | Building Permit Related(FS) | FS - Sprinkler Shop Drawing - To renovate the interior central atrium space of the ROM. Scope includes new skylight, feature stair, gallery wall openings, and new level raised floor. | — | Open |
| Aug 28, 2026 | Interior Alterations | Proposed interior alterations on the third floor in the area of rooms 318, 320, 322, 323, 324, and 325 and related electrical work. | $250K | Open |
| May 25, 2026 | Building Permit Related(PS) | Plumbing - To renovate the interior central atrium space of the ROM. Scope includes new skylight, feature stair, gallery wall openings, and new level raised floor. | — | Open |
| May 25, 2026 | Multiple Projects | To renovate the interior central atrium space of the ROM. Scope includes new skylight, feature stair, gallery wall openings, and new level raised floor. | $65.0M | Open |
| May 25, 2026 | Building Permit Related(MS) | HVAC - To renovate the interior central atrium space of the ROM. Scope includes new skylight, feature stair, gallery wall openings, and new level raised floor. | — | Open |
| Feb 17, 2026 | Building Permit Related(PS) | Rev 02 - Modifcations to the HVAC and plumbing distribution. Minor update to the duct work to add an access door for exhaust duct work. Deletion of fire damper supply and install scope at the B1 level due to existing fire damper being located. Fire standpipe replacement scope deletion. Revision 01 - | — | Open |
| Feb 17, 2026 | Building Permit Related(MS) | rEV 03 - Modifcations to the HVAC and plumbing distribution. Minor update to the duct work to add an access door for exhaust duct work. Deletion of fire damper supply and install scope at the B1 level due to existing fire damper being located. Fire standpipe replacement scope deletion. Revision # 2 | — | Open |
| Feb 13, 2026 | Sprinklers | Proposal to remove and reinstall fire protection at infill portion at ROM. (Before the bridge at 90 Queen's Park (Which is connected to 100 QP) is demolished) | $10K | Open |
| Nov 28, 2025 | Demolition | Proposed demolition of the building (McLaughlin Planetarium), excluding foundations | $3.0M | Demolition |
| Nov 28, 2025 | Other(BA) | Proposed infill portion of south wall - facade retrofit after demolishing planetarium (including connection between both planetarium and museum) | $350K | Open |
| Sep 29, 2025 | Interior Alterations | Theatre service space/back of house remediation/upgrades, and front of house theatre audience space renovation - "University of Toronto"Convenience address is 80 Queen's Park | $8.0M | Open |
| Sep 29, 2025 | Building Permit Related(MS) | HVAC - Theatre service space/back of house remediation/upgrades, and front of house theatre audience space renovation - "University of Toronto"Convenience address is 80 Queen's Park | — | Open |
| Sep 19, 2025 | Alternative Solution | Alternative Solution for the proposed wood ceiling for the proposed renovations to the Royal Ontario Museum (ROM), related to permit #23_166554_BLD. | — | Closed |
| Jul 9, 2025 | Building Permit Related(MS) | Rev. 1 - Revision for mechanical - fire dampers. equipment schedules, sprinkler layout, minor modification to existing grilles, diffusers and duct layout, etc. - See cover letter for detailed description.HVAC - Proposal to construct interior alterations on first floor. | — | Open |
| Jul 7, 2025 | Building Permit Related(PS) | Rev. 1 - Revision for mechanical, minor changes to sinks at Gridline 4 and associated solid interceptor on basement level.Plumbing - Proposal to construct interior alterations on first floor. | — | Open |
| Jun 19, 2025 | Multiple Projects | REVISION #4 - modifcations to the HVAC and plumbing distribution. Minor update to the configuration of the below grade Pump Rm. REVISION #3- as per the bubbled drawingsInterior renovations to the Royal Ontario Museum related to the Bloor Street entrance. | — | Open |
| May 15, 2025 | Interior Alterations | REVISION - revised sprinkler systemProposal to construct interior alterations on first floor. | — | Open |
| Feb 28, 2025 | Inside and Outside Drains | REVISION 01: This permit permit is being submitted to remove the crossing out for the exterior work related to the permit. Drain - Interior and Exterior renovations to the Royal Ontario Museum related to the Bloor Street entrance. | — | Open |
| Jan 17, 2025 | Building Permit Related(MS) | HVAC - Proposed addition of the boiler and electrical room on the existing mechanical penthouse level. Relocation of roof drains and addition of new floor drains in the new boiler room. | — | Closed |
| Jan 17, 2025 | Building Permit Related(PS) | Plumbing - Proposed addition of the boiler and electrical room on the existing mechanical penthouse level. Relocation of roof drains and addition of new floor drains in the new boiler room. | — | Open |
| Jan 17, 2025 | Addition(s) | Proposed addition of the boiler and electrical room on the existing mechanical penthouse level. Relocation of roof drains and addition of new floor drains in the new boiler room. | $200K | Open |
| Nov 21, 2024 | Building Permit Related(MS) | Revision 01: changes listed in cover letterHVAC - Proposal for interior alteration to existing building for on-site alcohol storage collection laboratory | — | Closed |
| Oct 15, 2024 | Alternative Solution | Proposal for an alternative solution to permit the use "street level entrance storey" in lieu of "first storey". | — | Closed |
| Aug 9, 2024 | Fire Alarm | Proposed: Fire alarm panel upgrade (conventional to addressable) with the following upgrades:Replacement of conventional fire alarm detectors with addressable devices on floors that are not sprinklered; Removal of fire alarm detectors on floors that are sprinklered; Addition of smoke detectors on to | $100K | Open |
| Apr 5, 2024 | Building Permit Related(PS) | Plumbing - Proposal for interior alteration to existing building for on-site alcohol storage collection laboratory | — | Closed |
| Apr 5, 2024 | Interior Alterations | Proposal for interior alteration to existing building for on-site alcohol storage collection laboratory | $750K | Closed |
| Dec 15, 2023 | HVAC: Groups A & B | Removal and disposal of existing HVAC system and installation of a new Air Handling Unit (AHU SF-26) | $691K | Open |
| Oct 11, 2023 | Building Permit Related(FS) | FS - Sprinkler Shop Drawing - Interior and Exterior renovations to the Royal Ontario Museum related to the Bloor Street entrance. | — | Closed |
| Sep 25, 2023 | Site Service | Replacement of existing exterior private on-site fire water mains due to deterioration. Installation of underground concrete valve chamber on private property for future maintenance purposes. | $100K | Closed |
| Jun 22, 2023 | Temporary Structures | ERECT TEMPORARY STRUCTURE FOR THE TORONTO JAZZ FESTSTART DATE JUN 23, TEAR DOWN 25 JUN. 2023. | — | Closed |
| Jun 21, 2023 | Temporary Structures | Proposal to construct a temporary structure on the roadway for the Toronto Jazz Festival.Setup date is June 23, 2023 and dismantled on June 25, 2023. | — | Closed |
| Oct 17, 2022 | Alternative Solution | Proposal to remove the existing 23m lengths of 38mm diamter fire hoses in every hose cabinet within the building | — | Open |
| Mar 26, 2021 | Backflow Prevention Devices (Water only) | Installation of backflow preventer device - The Gardiners Museum | $5K | Open |
| Feb 23, 2021 | Interior Alterations | Proposal for interior alterations to existing museum | $400K | Open |
| Feb 19, 2021 | Building Permit Related(MS) | HVAC - Proposal for interior renovations to part basement rooms 079 and 080 located at Edward Johnson building. | — | Open |
| Dec 18, 2020 | Interior Alterations | Proposal for interior alterations to existing museum for new gallery space | $4.0M | Closed |
| Dec 18, 2020 | Building Permit Related(MS) | HVAC - Proposal for interior alterations to existing museum for new gallery space | — | Open |
| Oct 21, 2020 | Other(BA) | Stone masonry repairs, including steel shelf angle replacement and off site heritage steel window conservation at the north south and patrial west (south end) of the East Wing | $1.1M | Open |
| Jul 24, 2020 | Interior Alterations | Proposal for interior renovations to part basement rooms 079 and 080 located at Edward Johnson building. | $280K | Open |
The 40 most recent of 216 permits on record. Figures come from the City’s active and cleared permit datasets, refreshed daily — what that covers, and what it misses.