The City of Toronto has 2,607 building permits on transit station,subway, bus terminal structures on record for Toronto, going back to 1999. Those permits created 0 homes and removed 2, a net change of -2. Declared construction value totals $12.1B. Half of the 2,283 permits issued here came through within 44 days of the application. The most recent permit was applied for Oct 29, 2026 at 1080 Millwood Rd.
- Permits on record
- 2,6071999–2026
- Declared construction value
- $12.1Bas filed, not adjusted
- Homes created
- 0dwelling units
- Homes removed
- 2net -2
- Typical wait
- 44 days17 days slower than the city
Permits issued per year
Zoning
- Most common zone
- CR42.6% of permits · by-law 40.10
- In detached-house zones
- 0.0%38.0% below the city’s 38.0%
- Permits with a zone
- 1,364of 2,607 on record
The zoning categories the permits in Transit Station,Subway, Bus Terminal fall in, under Zoning By-law 569-2013. These are the City's own category names. This counts permits, not land: it says where the building work happened under which rules, not how the area is carved up. What each zone allows, and what gets built in it.
Most common work
Structures worked on
Postal areas
Most recent permits
| Issued | Address | Work | What was filed | Value | Status |
|---|---|---|---|---|---|
| Oct 29, 2026 | 1080 Millwood Rd | Site Service | Proposal for the installation of a temporary water connection to provide a water supply required to support the approved construction activities associated with the Guideway Piers. | $465K | Open |
| Oct 29, 2026 | 139 St George St | Interior Alterations | Proposal for Installation of roof edge railings, roof mounted stair and ladder ports at TTC's St. George Station -St. George Entrance | $1.6M | Open |
| Oct 29, 2026 | 50 Village Station Rd | Interior Alterations | Proposal for construction of a service overhead working platform within the OLOMSF maintenance bld. Existing maintenance bld permit no. 24 247681 BLD 00 NB; includes access stairs with an approx length as well as ladders. | $93.7M | Open |
| Oct 29, 2026 | 4651 Sheppard Ave E | Other(BA) | Proposed construction of a noise barrier wall to protect the adjacent building from the noise and vibration generated by the construction activities. | $2.0M | Open |
| Oct 28, 2026 | 8 Bedford Rd | Interior Alterations | Proposal for installation of roof edge railings and ladder port at TTC's St. George Station - Bedford Entrance. | $1.6M | Open |
| Oct 28, 2026 | 22 Chester Ave | Interior Alterations | Proposal for installation of roof edge railings and ladder port at TTC's Chester Station. | $1.6M | Open |
| Oct 28, 2026 | 6 Spadina Rd | Interior Alterations | Proposal for installation of roof edge railings, roof mounted stair, fixed ladder and ladder port at TTC's Spadina Stn -Main Entrance | $1.6M | Open |
| Oct 28, 2026 | 28 Overlea Blvd | Building Permit Related (DR) | Drain - The proposed Thorncliffe Park Station is located at the Overlea Boulevard and Thorncliffe Park Drive intersection and is constrained by Overlea Boulevard to the south, and Thorncliffe Park Drive to the west. Public access to the building will be provided at ground level via entrances at Over | — | Open |
| Oct 28, 2026 | 769 Broadview Ave | Interior Alterations | Proposal for installation of roof edge railings and ladder port at TTC's Broadview Stn. | $1.6M | Open |
| Oct 28, 2026 | 61 Front St W | Fire Alarm | REV 03: Revision to permit due to change of height to sprinkler layout in the Truck Tunnel. REV 02 - Revision to sprinkler drawings - Revision to permit due to elevation change to sprinkler layout in the Truck Tunnel. REV 01 - Revision descriped in application formThe scope of work includes the remo | — | Open |
| Oct 28, 2026 | 400 Greenwood Ave | Other(BA) | Proposal for interior alterations (replacement of pump pit access hatch, localized concrete repairs, alterations and installation of pit ladders and pump control rework). | $200K | Open |
| Oct 28, 2026 | 61 Front St W | Building Permit Related(PS) | REV 01: Providing plumbing system design for the USEP building. Related to Main Building Permit 22 237137 BLD 00 NBPlumbing - Construction of new platforms, with canopies and vertical access elements, such as stairs and elevators and a new concourse area below the new platforms that will connect the | — | Open |
| Oct 28, 2026 | 9A Walmer Rd | Interior Alterations | Proposal for installation of roof edge railings and ladder port at TTC's Spadina Stn. - Walmer Entrance | $1.6M | Open |
| Oct 28, 2026 | 10 Overlea Blvd | Site Service | Proposed installation of a temporary water connection to provide a water supply required to support the approved construction activities associated with the guideway piers. | $465K | Open |
| Oct 28, 2026 | 600 Bloor St E | Interior Alterations | Proposal for installation of horizontal life lines and roof mounted stair at TTC's Castle Frank Station. | $1.6M | Open |
| Oct 27, 2026 | 400 Greenwood Ave | Building Permit Related(MS) | HVAC - Proposed replacement of the existing 3T bridge crane with a new 10T bridge crane addition within the TTC train maintenance facility, and all associated mechanical work. | — | Open |
| Oct 27, 2026 | 400 Greenwood Ave | Interior Alterations | Proposed replacement of the existing 3T bridge crane with a new 10T bridge crane addition within the TTC train maintenance facility, and all associated mechanical work. | $10.6M | Open |
| Oct 26, 2026 | 1711 McCowan Rd | Site Service | Proposed 1200mm sanitary manhole installed along with the connection to the existing 250mm AC pipe as per City standards on private property. This is meant to support the construction SOE activities taking place on this site. | $40K | Open |
| Oct 26, 2026 | 2365 Dundas St W | Building Permit Related(PS) | 26 243273 PLB 00 PS | — | Open |
| Oct 26, 2026 | 2365 Dundas St W | Building Permit Related(MS) | HVAC - Proposed replacement of passenger elevator between westbound platform and concourse level of the Station. Minor concrete work at elevator lintels and jambs repairs to damaged walls, Minor concrete repairs within pit, re-level pit to provide slope to drain, replacement of CCTV camera and conne | — | Open |
| Oct 26, 2026 | 2365 Dundas St W | Interior Alterations | Proposal for interior alterations at Dundas West Station to replace the passenger elevator between the westbound platform and concourse level, localized concrete repairs (elevator lintels, jambs, train way/pit alterations), localized repairs to damaged walls, replacement of CCTV camera, connection o | $2.0M | Open |
| Oct 26, 2026 | 160 Transit Rd | Other(BA) | Proposal for multiple projects (replace access hatches at pump pit, localized concrete repairs, install pit ladder and pump control rework). | $200K | Open |
| Oct 23, 2026 | 61 Front St W | Building Permit Related(MS) | REV 01: Providing heating, ventilation and air conditioning system design for the USEP building. Related to main building permit 22 237137 BLD 00 NBHVAC - Construction of new platforms, with canopies and vertical access elements, such as stairs and elevators and a new concourse area below the new pl | — | Open |
| Oct 23, 2026 | 1 IBMS WARD 05 | Site Service | REV 01: per the attached Response LetterDrain - Proposed new Caledonia GO Station. | — | Open |
| Oct 22, 2026 | 991 Woodbine Ave | Interior Alterations | Proposal to install Fall Prevention Railings and roof access. (TTC Woodbine Subway Station) | $81K | Open |
| Oct 20, 2026 | 819 Bathurst St | Multiple Projects | Replacement of passenger elevator between eastbound platform and concourse level of the Station. Minor concrete work at elevator lintels and jambs repairs to damaged walls, Minor concrete repairs within pit, re-level pit to provide slope to drain, replacement of CCTV camera and connection of elevato | $2.0M | Open |
| Oct 20, 2026 | 21 Lower Spadina Ave | Fire Alarm | Fire Alarm replacement and upgrades at TTC Harbourfront Substation. | $300K | Open |
| Oct 19, 2026 | 10 Bay St | Other(BA) | Proposal for interior alterations (replacement of pump pit access hatch, localized concrete repairs and pump control rework). | $200K | Open |
| Oct 19, 2026 | 5050 Sheppard Ave E | Other(BA) | Proposal to add electronic level monitoring to one (1) existing 2,900 L volume Transformer Room Spill Tank (Tank MA1). Decommission and remove one (1) existing 2,325 L volume Flammable Storage Room Spill Tank (Tank ID MA2), piping, and associated appurtenances. Existing Veeder-Root TLS-450 console t | $550K | Open |
| Oct 19, 2026 | 10 Linnsmore Cres | Interior Alterations | Proposal to install Fall Prevention Railings and roof access (TTC Greenwood Subway Station). | $81K | Open |
| Oct 19, 2026 | 5050 Sheppard Ave E | Building Permit Related(PS) | Plumbing - Proposal to add electronic level monitoring to one (1) existing 2,900 L volume Transformer Room Spill Tank (Tank MA1). Decommission and remove one (1) existing 2,325 L volume Flammable Storage Room Spill Tank (Tank ID MA2), piping, and associated appurtenances. Existing Veeder-Root TLS-45 | — | Open |
| Oct 16, 2026 | 30 Donlands Ave | Interior Alterations | Proposal to install Fall Prevention Railings and roof access (TTC Donlands Subway Station). | $81K | Open |
| Oct 15, 2026 | 4 Glenayr Rd | Other(BA) | Proposal for replacement of pit hatches and ladder in train way pump room 3S128 at TTC's Glenayr Emergency Exit Building (ESB). | $200K | Open |
| Oct 15, 2026 | 4 Glenayr Rd | Building Permit Related (DR) | Drain - Proposal for replacement of pit hatches and ladder in train way pump room 3S128 at TTC's Glenayr Emergency Exit Building (ESB). | — | Open |
| Oct 9, 2026 | 400 Greenwood Ave | Interior Alterations | Proposal for non-structural roofing replacement for the Boiler Building at TTC¿s Greenwood Yard Complex, 400 Greenwood Avenue. | $500K | Open |
| Oct 8, 2026 | 1350 Eglinton Ave W | Other(PS) | Plumbing work for morningside qsr kiosk | $25K | Open |
| Oct 7, 2026 | 1300 Eglinton Ave W | Re-Roofing/Re-Cladding | Proposal for roof rehabilitation project of the respective roof areas in the courtyard. The work includes removal of existing metal roof panels, gutters and downspouts, and installation of new metal roof, gutters, downspouts and new de-icing snow cables at all metal roof eaves, including heat tracin | $630K | Open |
| Oct 6, 2026 | 3 Dundas St E | Other(BA) | Proposed installation of platform barriers at TMU Station as a safety pilot program introduced by TTC. The design consists of 14 such barriers along each of the northbound and southbound platforms at the TMU station. | $1.5M | Open |
| Oct 6, 2026 | 36 North Queen St | Inside and Outside Drains | Drain - Proposal for site trailers with the elevated walkway and canopy roof structure (143.98 sqm) serve as field offices for staff working on the GO Expansion On-Corridor project. | $100K | Open |
| Oct 5, 2026 | 1 IBMS WARD 01 | Inside and Outside Drains | Drain - Resources Road Logistic Hub consists of two single-story, pre-assembled modular trailers. These trailers are connected by an exterior elevated walkway, served by three access points: stairs at each end and a ramp in the middle. The walkway is covered by a continuous canopy. Together, they ef | $10K | Open |