Street · 5361 of 8,567 by permit count
Building permits on Transfer Pl
The City of Toronto has 21 building permits on record for Transfer Pl, going back to 2001. Declared construction value totals $26.2M. The most recent permit was issued May 21, 2024 at 1 Transfer Pl.
- Permits on record
- 212001–2024
- Declared construction value
- $26.2Mas filed, not adjusted
- Homes created
- 0dwelling units
- Homes removed
- 0net +0
Permits issued per year
20012024 (part year)
Most common work
Structures worked on
Most recent permits
| Issued | Work | What was filed | Value | Status |
|---|---|---|---|---|
| May 21, 2024 | Building Permit Related(MS) | HVAC - Proposal of Installation of new switchgear and breaker; floor resurfacing; replacementof rooftop ventilation cowls | — | Open |
| May 21, 2024 | Building Permit Related(PS) | Plumbing - Proposal of Installation of new switchgear and breaker; floor resurfacing; replacementof rooftop ventilation cowls | — | Open |
| May 21, 2024 | Interior Alterations | Proposal of Installation of new switchgear and breaker; floor resurfacing; replacementof rooftop ventilation cowls | $4.4M | Open |
| Jan 31, 2023 | Sprinklers | Setting up the new sprinkler system for the new building - see 19 245708 | $200K | Closed |
| Jun 6, 2022 | Other(BA) | Complete the removal of the existing wooden staircase, steel handrail, rail wood, concrete pad, concrete curb, asphalt, trees, soil and construction of new concrete staircase, two steel handrails, concrete barrier curbs, concrete outlet, grass swale, and warning sign. | $100K | Closed |
| Feb 16, 2022 | Other(DS) | Proposed: New steel-framed building, and associated electrical and mechanical services | $6.1M | Closed |
| Jul 15, 2019 | Alter: Boiler/Furnace/AC Replacement | replace heating/cooling system to office and lunchroom | $100K | Closed |
| Jun 19, 2019 | Piping: Other Buildings | replace heating/cooling system to office and lunchroom | $100K | Closed |
| Jun 26, 2017 | Solar Collector | REVISION - structural changes as per the drawingsProposal to construct a rooftop solar photovoltaic system consisting of 1125 CS6X-320 320 Watt panels at a 10/15-degree tilt. | — | Closed |
| May 30, 2016 | Manholes/Catch Basins/Sumps/Interceptors | INSTALL NEW OIL INTERCEPTOR AT WASTE TRANSFER STATION | $150K | Closed |
| Nov 12, 2013 | Building Permit Related(FS) | FS - Sprinkler Shop Drawing - Waste transfer station floor slab repair with mass concrete fill | — | Closed |
| Apr 24, 2013 | Garage Repair/Reconstruction | Waste transfer station floor slab repair with mass concrete fill | $15.0M | Closed |
| Jun 1, 2012 | Backflow Prevention Devices (Water only) | Backflow preventer at waste transfer station | $8K | Closed |
| May 27, 2004 | New Building | SCARBOROUGH TRANSFER STATION, CONSTRUCTION OF A FABRIC COVERED BUILDING - REVISION TO ADD NEW FIRE HOSE CABINET AND NEW STANDPIPE | — | New build |
| Mar 23, 2004 | New Building | SCARBOROUGH TRANSFER STATION, CONSTRUCTION OF VALVE SHELTER FOR A FABRIC COVERED BUILDING | $10K | New build |
| Mar 12, 2004 | New Building | SCARBOROUGH TRANSFER STATION, CONSTRUCTION OF VALVE SHELTER FOR A FABRIC COVERED BUILDING *SITE INSPECTION FOLDER* - | — | New build |
| Mar 5, 2004 | Building Permit Related(PS) | Plumbing - SCARBOROUGH TRANSFER STATION, CONSTRUCTION OF A FABRIC COVERED BUILDING - New Building | — | Closed |
| Mar 5, 2004 | Building Permit Related(MS) | HVAC - SCARBOROUGH TRANSFER STATION, CONSTRUCTION OF A FABRIC COVERED BUILDING - New Building | — | Closed |
| Mar 1, 2004 | New Building | SCARBOROUGH TRANSFER STATION, CONSTRUCTION OF A FABRIC COVERED BUILDING *SITE INSPECTION FOLDER* - | — | New build |
| Feb 16, 2004 | New Building | SCARBOROUGH TRANSFER FACILITY, CONSTRUCTION OF A FABRIC COVERED BUILDING | — | New build |
| Oct 29, 2001 | Other(MS) | Ventilation modification to household hazardours depot. Internal application | $20K | Closed |
The 21 most recent of 21 permits on record. Figures come from the City’s active and cleared permit datasets, refreshed daily — what that covers, and what it misses.