Street · 3140 of 8,565 by permit count
Building permits on Pearl St
The City of Toronto has 54 building permits on record for Pearl St, going back to 1996. Declared construction value totals $21.2M. The most recent permit was issued Oct 30, 2025 at 120 Pearl St.
- Permits on record
- 541996–2025
- Declared construction value
- $21.2Mas filed, not adjusted
- Homes created
- 0dwelling units
- Homes removed
- 0net +0
Permits issued per year
20002025 (part year)
Most common work
Structures worked on
Where this street runs
Yonge-Bay Corridor 34 permits
Wellington Place 10 permits
Most recent permits
| Issued | Work | What was filed | Value | Status |
|---|---|---|---|---|
| Oct 30, 2025 | Sign Building Permit Related | 1 WALL SIGN**ENWAVE GREEN HEAT** | — | Open |
| Nov 27, 2024 | Building Permit Related(PS) | Plumbing - Removal of the existing roof deck and roofing on the entire existing plant and replacing with new. | — | Open |
| Nov 27, 2024 | Re-Roofing/Re-Cladding | Removal of the existing roof deck and roofing on the entire existing plant and replacing with new. | $2.0M | Open |
| Apr 26, 2023 | Other(BA) | Curtainwall replacement on exterior of plant. No interior work.640 sm | $700K | Open |
| Apr 24, 2023 | Fire Alarm | Replacement of fire alarm control panel | $18K | Open |
| Jan 18, 2023 | Building Permit Related(PS) | Plumbing - Proposal for a building addition to the industrial building (Steam Plant) to house a new heat pump plant. See also 21 247571 ZPR. | — | Closed |
| Jan 18, 2023 | Addition(s) | Proposal for a building addition to the industrial building (Steam Plant) to house a new heat pump plant. See also 21 247571 ZPR. | $8.5M | Open |
| Jan 18, 2023 | Building Permit Related(MS) | HVAC - Proposal for a building addition to the industrial building (Steam Plant) to house a new heat pump plant. See also 21 247571 ZPR. | — | Open |
| Dec 13, 2022 | Building Permit Related(FS) | FS - Sprinkler Shop Drawing - Proposal for a building addition to the industrial building (Steam Plant) to house a new heat pump plant. See also 21 247571 ZPR. | — | Closed |
| Jul 14, 2021 | Building Permit Related(PS) | Plumbing - Installation of 3 roof drains (1 at west roof, 1 at central high roof, 1 at east roof), associated reinforcing of roof structure to accomodate openings for roof drains, and re-roofing of central portion of high roof and north half of east roof. | — | Closed |
| Jul 14, 2021 | Re-Roofing/Re-Cladding | Installation of 3 roof drains (1 at west roof, 1 at central high roof, 1 at east roof), associated reinforcing of roof structure to accomodate openings for roof drains, and re-roofing of central portion of high roof and north half of east roof. | $248K | Closed |
| Jun 5, 2020 | Backflow Prevention Devices (Water only) | install backflow device | $12K | Closed |
| Feb 20, 2020 | Interior Alterations | Revison #1 - Enwave - Convert an existing, below-grade oil storage room into a chiller room, in an Existing Industrial Building. | — | Open |
| Feb 19, 2020 | Building Permit Related(MS) | HVAC Revision #1 - Enwave - Convert an existing, below-grade oil storage room into a chiller room. | — | Open |
| Sep 4, 2019 | Interior Alterations | Proposed interior alterations in basement of existing industrial building, as well as removal of existing sprinkler system and replacement with new. | $7K | Open |
| Jun 3, 2019 | Interior Alterations | Proposed Interior Alterations to Existing Control Room and Vestibule within the Existing 'Steam Plant' (Existing Industrial Building). | $25K | Closed |
| Aug 2, 2018 | Interior Alterations | Proposal for interior alterations to existing exit stair and lobby on ground floor. | $20K | Closed |
| Apr 26, 2017 | Sprinklers | Install new Sprinklers system for protection | $1K | Closed |
| Jun 9, 2016 | Addition(s) | Proposal to construct a building addition containing a new mechanical shaft to an existing builidng. | $50K | Open |
| Feb 29, 2016 | Interior Alterations | Proposal for interior alterations on the basement and mezzanine level, exit stair will be removed, "Enwave Energy Corporation" | $250K | Open |
| Aug 13, 2015 | Interior Alterations | Proposal for slab repair to the interior of the existing steam plant. | $238K | Closed |
| Aug 5, 2015 | Interior Alterations | Proposal for interior alterations to second floor office space, "RNAO" | $100K | Closed |
| Jul 3, 2015 | Electromagnetic Locks | Install one new Electromagnetic Locks | $2K | Closed |
| Jun 18, 2015 | Demolition | Proposal to demolish two storey mixed use non residential building | — | Demolition |
| Jun 18, 2015 | Building Permit Related(MS) | HVAC - Proposal to install rooftop cooling towers complete with platform and stairs in an existing power/steam plant. | — | Open |
| Jun 18, 2015 | Building Permit Related(PS) | Plumbing - Proposal to install rooftop cooling towers complete with platform and stairs in an existing power/steam plant. | — | Open |
| Jun 18, 2015 | Other(BA) | Proposal for gound floor and basement concrete repairs in existing steam power plant. | $5.0M | Open |
| Jul 30, 2014 | Garage Repair/Reconstruction | Proposal for gound floor and basement concrete repairs in existing steam power plant. | $200K | Open |
| Jul 16, 2013 | Other(BA) | Proposal to replace window openings on west face and interior alterations to extend platform floor on the ground floor of existing steam power plant. | $200K | Closed |
| Dec 23, 2011 | Fire Alarm | Proposal to upgrade the fire alarm system in an existing office building. Convenience address 154-158 Pearl St. | $57K | Open |
| Jun 14, 2011 | Other(BA) | Proposal to construct structural steel support and associated access stair on roof of existing steam plant to facilitate the installatin of new roof top backup generator. Also see related building permit 10-153006 BLD. | $750K | Closed |
| Oct 15, 2010 | Backflow Prevention Devices (Water only) | Proposal to install one back flow prevention device. Building comprised of Office units. Convenience address 154 Pearl Street. | $2K | Closed |
| Sep 27, 2010 | Sprinklers | Sprinkler permit in conjunction with 10 153006 BLD. | $750K | Closed |
| Sep 20, 2010 | Building Permit Related(MS) | HVAC - permit for interior alterations to basement of existing power plant - 141 m2 | — | Closed |
| Jul 27, 2010 | Backflow Prevention Devices (Water only) | Proposal to install one back flow prevention device to office building. | $1K | Closed |
| Jul 13, 2010 | Interior Alterations | permit for interior alterations to basement of existing power plant - 141 m2 | $200K | Closed |
| Jun 10, 2010 | Interior Alterations | Proposal to construct mechanical platform above ground floor level. Platform to be used for boiler equipment. | $750K | Closed |
| May 27, 2009 | Other(BA) | Proposal to increase occupant load of multi (3) their roof top patio to 300. See Bld permit # 98-021 257. | $1K | Closed |
| Mar 27, 2009 | Addition(s) | Proposal to construct addition to front of building for new entrance to existing office building "Registered Nurses Association of Ontario" (2.32m2). | $5K | Closed |
| Nov 5, 2008 | Shoring | Excavation and shoring to facilitate installation of 3 new diesel fuel tanks. | $115K | Closed |
The 40 most recent of 54 permits on record. Figures come from the City’s active and cleared permit datasets, refreshed daily — what that covers, and what it misses.