The City of Toronto has 4,054 building permits on record for the Church-Wellesley neighbourhood, going back to 1989. Those permits created 4,876 homes and removed 122, a net change of +4,754. Declared construction value totals $2.1B. Half of the 3,788 permits issued here came through within 26 days of the application. The most recent permit was issued Oct 28, 2026 at 43 Wellesley St E.

Outline map of Toronto with the Church-Wellesley neighbourhood shaded
Church-Wellesley within Toronto. Boundary from the City’s neighbourhood layer, drawn to the same projection on every page so two maps can be compared.
Permits on record
4,0541989–2026
Declared construction value
$2.1Bas filed, not adjusted
Homes created
4,876dwelling units
Homes removed
122net +4,754
Typical wait
26 days1 day faster than the city

Permits issued per year

20002026 (part year)

Zoning

Most common zone
CR74.2% of permits · by-law 40.10
In detached-house zones
0.0%38.0% below the city’s 38.0%
Permits with a zone
3,458of 4,054 on record
  • Commercial Residential2,567 · 74%
  • Residential843 · 24%
  • Open Space48 · 1%

The zoning categories the permits in Church-Wellesley fall in, under Zoning By-law 569-2013. These are the City's own category names. This counts permits, not land: it says where the building work happened under which rules, not how the area is carved up. What each zone allows, and what gets built in it.

Minor variances at the Committee of Adjustment

Applications on record
75since 2016
Approved
95.0%4.2% above the city · 60 decided
Median time to a decision
149 days29 days slower than the city

Some projects in Church-Wellesley need the Committee of Adjustment to approve a minor variance from the zoning by-law before a building permit can be applied for at all. Where that applies, the committee’s clock runs first and the permit wait above starts only once it has stopped. Back to back, that is about 175 days, not the 26 days the permit figure alone suggests. How variances work, and the approval rates.

Most common work

Structures worked on

Postal areas

Most recent permits

Issued Address Work What was filed Value Status
Oct 28, 2026 43 Wellesley St E Building Permit Related(MS) HVAC - Interior renovation of existing X-ray Rooms 240, 219, 236 and 231, to be completed in four sequential phases, with one room renovated at a time. The project also included the installation of three new X-ray machines during Phases 2, 3 and 4. — Open
Oct 28, 2026 43 Wellesley St E Interior Alterations Interior renovation of existing X-ray Rooms 240, 219, 236 and 231, to be completed in four sequential phases, with one room renovated at a time. The project also included the installation of three new X-ray machines during Phases 2, 3 and 4. $19.0M Open
Oct 28, 2026 43 Wellesley St E Building Permit Related(PS) Plumbing - Interior renovation of existing X-ray Rooms 240, 219, 236 and 231, to be completed in four sequential phases, with one room renovated at a time. The project also included the installation of three new X-ray machines during Phases 2, 3 and 4. — Open
Oct 27, 2026 667 Yonge St Interior Alterations Proposal to increase occupancy load and change occupancy to group A-2 — Open
Oct 23, 2026 175 Bloor St E Interior Alterations REV01: Revision for structural engineering drawings for telescoping partition.Proposal for interior alterations to existing office space - UNITS 600 & 603, "CMTO" — Open
Oct 20, 2026 2 Gloucester St Other(MS) REV: Proposed revision for ventilation adjustments based on as-built conditionProposal to replace heating plant, domestic hot water heating, potable water distribution, ventilation and air conditioning systems. — Open
Oct 20, 2026 110 Charles St E Other(MS) REV 01: Revision to permit to include two risers Proposal to replace heating riser. — Open
Oct 19, 2026 175 Bloor St E Building Permit Related(MS) HVAC - Office new fit out to accommodate new tenant. HVAC to reflect new ceiling. — Open
Oct 19, 2026 175 Bloor St E Building Permit Related(PS) Plumbing - Office new fit out to accommodate new tenant. HVAC to reflect new ceiling. — Open
Oct 15, 2026 15 Dundonald St Interior Alterations REV01: Revision as bubbled on drawings.Proposal for interior alterations to convert existing storage into office for management. — Open
Oct 15, 2026 175 Bloor St E Interior Alterations Office new fit out to accommodate new tenant. HVAC to reflect new ceiling. $100K Open
Oct 14, 2026 665 Yonge St Interior Alterations Proposed interior alterations to convert vacant suite into beauty salon. $40K Open
Oct 14, 2026 665 Yonge St Building Permit Related(PS) Plumbing - Proposed interior alterations to convert vacant suite into beauty salon. — Open
Oct 14, 2026 665 Yonge St Building Permit Related(MS) HVAC - Proposed interior alterations to convert vacant suite into beauty salon. — Open
Oct 13, 2026 330 Jarvis St Building Permit Related(MS) HVAC - Replacement of the existing make up air unit, DHW storage tank and boilers including ductwork, piping, pumps, etc. in the penthouse mechanical room. — Open
Oct 13, 2026 55 Bloor St E Other(MS) Proposed make-up air replacements $523K Open
Oct 13, 2026 330 Jarvis St Interior Alterations Replacement of the existing make up air unit, DHW storage tank and boilers including ductwork, piping, pumps, etc. in the penthouse mechanical room. $105K Open
Oct 5, 2026 620 Church St Re-Roofing/Re-Cladding PROPOSED EXTERIOR WALL REPAIRS $320K Open
Sep 30, 2026 15 Dundonald St Building Permit Related(MS) REV01: As bubbled on drawings.HVAC - Proposal for interior alterations to convert existing storage into leasing office and storage. — Open
Sep 28, 2026 665 Yonge St Sign Building Permit Related One wall sign.***SIGNATURE HAIR STUDIO*** — Open
Sep 25, 2026 519 Church St Other(BA) Proposal for installation of an art work on the front face of existing building. Weight 150kg $25K Open
Sep 23, 2026 475 Yonge St Interior Alterations Interior alteration to combine an existing gym room and adjacent pool room into one fitness room. $456K Open
Sep 23, 2026 475 Yonge St Building Permit Related(MS) HVAC - Interior alteration to combine an existing gym room and adjacent pool room into one fitness room. — Open
Sep 11, 2026 601 Yonge St Interior Alterations Revision to include the fire alarm & exit lighting layout as it was not approved in the original submission. Proposal for interior alterations to an existing convenience store. — Closed
Sep 9, 2026 100 Hayden St Electromagnetic Locks Maglock Installation $20K Open
Sep 1, 2026 20R Maitland St Electromagnetic Locks Installation of one Electromagnetic Lock on ground floor. $5K Open
Sep 1, 2026 175 Bloor St E Building Permit Related(MS) HVAC - Proposed interior alterations to unit 1101 to expand existing boardroom and add two (2) small offices. — Open
Aug 28, 2026 117 Bloor St E Sign Building Permit Related 1 ILLUMINATED WALL SIGN ** ST. ANDREWS UNITED CHURCH ** — Open
Aug 27, 2026 175 Bloor St E Interior Alterations Proposed interior alterations to unit 1101 to expand existing boardroom and add two (2) small offices. $120K Open
Aug 25, 2026 6 Gloucester St Building Permit Related(MS) REVISION -02 : MEASURE 'N' VESTIBULE FRESH AIR SUPPLY FAN ADDED ON GROUND FLOORHVAC - Proposal for a new 34-storey mixed use rental apartment building containing 232 rental units with retail uses at grade and 2 levels below grade parking. Address includes 6 and 8 Gloucester Street.REVISION 01: Measu — Open
Aug 21, 2026 411 Church St Building Permit Related(PS) Plumbing - Proposed interior alterations to convert existing retail store to dental office. — Open
Aug 21, 2026 411 Church St Building Permit Related(MS) HVAC - Proposed interior alterations to convert existing retail store to dental office. — Open
Aug 14, 2026 175 Bloor St E Building Permit Related(MS) HVAC - Expansion of boardroom, Addition of two small offices. — Closed
Aug 14, 2026 175 Bloor St E Interior Alterations Expansion of boardroom, Addition of two small offices. $120K Closed
Aug 12, 2026 411 Church St Interior Alterations Proposed interior alterations to convert existing retail store to dental office. $100K Open
Jul 30, 2026 175 Bloor St E Interior Alterations Interior alterations to combine suites 701 and 702 into a single tenant unit, including removal of the demising wall and relocation of the entrance door to swing in the direction of egress travel. $100K Closed
Jul 24, 2026 109 Gloucester St Interior Alterations REV 01: Proposed 4th unit in basementProposal for interior alterations, including the replacement of the staircase from the ground floor to the basement and the addition or replacement of non-structural walls. There are no changes to any exterior doors or windows. New beams and columns are being add — Open
Jul 22, 2026 175 Bloor St E Interior Alterations Proposal for interior alterations for suites 701 & 702 to make it into one suite. Entrance door be removed and relocated to swing with path of travel. $100K Closed
Jul 15, 2026 71 Charles St E Garage Repair/Reconstruction Proposed repairs to the underground parking facility, performing localized concrete repairs to the property parking garage ramp, as well as waterproofing repairs $260K Open
Jul 10, 2026 43 Wellesley St E Building Permit Related(MS) HVAC - Interior renovation of existing X-ray Rooms 240, 219, 236 and 231, to be completed in four sequential phases, with one room renovated at a time. The project also included the installation of three new X-ray machines during Phases 2, 3 and 4. — Closed

The 40 most recent of 4,054 permits on record. Figures come from the City’s active and cleared permit datasets, refreshed daily — what that covers, and what it misses.

Source
City of Toronto Open Data
Dataset
Building permits, active + cleared
Records
4,054
Data through
2026-10-28